The Noida Authority on Saturday afternoon convened a meeting to discuss the status of demolition of the Supertech twin towers, following directions of the Supreme Court in its July 29 order. The buildings, Apex and Ceyane, are located in Sector 93A. The demolition is fixed for August 21 at 2.30 pm, which is just under a fortnight away.
Information sought by CBRI as well as requisite details supplied by Supertech Ltd. and Edifice Engineering, a construction and demolition waste management plan, preparations made for countering the effect of dust created due to the demolition on the green area and parks located in ATS Village and Supertech Emerald Court (buildings in the vicinity) and steps to be taken for securing GAIL’s gas pipeline were discussed.
Based on the discussions certain directions were taken. A note shared by the authority states that CBRI found that Supertech Ltd. has not provided certain details pertaining to the structural audit and the same are to be provided to CBRI by August 7. After receiving the requisite information, CBRI will submit its report to Noida Authority by August 9, pursuant to which the authority will file a status report by August 11 before the Supreme Court.
Noida Authority will regularly monitor work carried out by Supertech Ltd. pertaining to the structural defects. Edifice Engineering will be working on suggestions provided by GAIL for protection of the gas pipeline. A meeting convened under the guidance of Additional CEO (P) to discuss preparations is to be undertaken for countering the effect of dust created due to the demolition on the green area and parks located in ATS Village and Supertech Emerald Court. For this, experts in Botany will also be invited to participate.
The analysis of the construction & demolition waste management plan submitted by Edifice Engineering to the Uttar Pradesh Pollution Control Board will be completed in a week.